Implementation Roadmap
- Category
-
- 2021
-
- 1st Quarter
- 2nd Quarter
- 3rd Quarter
- 4th Quarter
-
- 2022
-
- First Half
- Second Half
- 2023~2031
Jamsil Sports•MICE Private Investment Project
Third-party proposal announcement (~’21.9)
Negotiation, implementation agreement, and design (’21.10.~’24.12.)
Construction (’26.~’31.)
Seoul Sports Complex Main Stadium Remodeling
Basic and detailed design (~’24.)
Construction (~’29.)
영동대로 지하공간 복합개발
Pre-construction administrative procedures and detailed design (~21.12)
Main construction (’22.~’28.)
Priority construction (’21.6~’22.2)
International Exchange Complex District Road Improvement
Basic and detailed design (~’24.)
Construction (~’29.)
Waterfront Space Development and Pedestrian Bridge Construction
Basic and detailed design (~’23.7.)
Construction (’23.8.~’26.12.)
Hyundai GBC Development
Construction (’20.5.~)
※ Schedules may be adjusted according to changes in project conditions