Implementation History
2008~2014
Announced Comprehensive Development Plan (Basic Concept)for COEX~Seoul Sports Complex Area
-
- ‘08.~’11.
- Established plan direction including spatial maintenance concept for public institution relocation sites
-
- ‘12.~’13.
- Reviewed introduced functions and feasibility
-
- ‘13.~’14.
- Prepared Comprehensive Development Plan (Basic Concept)
2014~2016
Prepared Implementation Plans forInternational Exchange Complex District Development
-
Public Sites (Seoul Sports Complex, Han River/Tancheon Area)
-
- ‘14.11.~’15.9.
- Conducted ideas competition from experts and citizens (3 times)
- ’15.1.~9. Conducted international expert competition
- ’14.11.~’15.5. Conducted citizen idea competition (2 times)
-
- ‘14.4.~’16.4.
- Established Seoul Sports Complex Area Master Plan
- ’16.4.25. Held press briefing on Seoul Sports Complex Area Master Plan
-
- ‘16.5.~7.
- Developed Underground Space of Yeongdong-daero
- ’16.5.2. Announced basic concept
- ’16.7.21. Initiated basic plan service order
-
Private Sites (Hyundai Motor Site)
-
- ‘15.7.~’16.2.
- Completed pre-negotiation
- Held 2 Working TF meetings, conducted 12 negotiation adjustment working meetings, held 6 expert consultations, operated 10 negotiation adjustment council meetings
- ‘16.2.17. Announced pre-negotiation results
-
- ‘16.2.~’16.9.
- Established District Unit Plan Decision (Modification) and Detailed Development Plan
- 3.~4. Conducted public inspection and related department consultation
- 4. Reported to city council
- 8.~9. Conducted review
-
‘14.4.~’16.9. Established Urban Management Plan for Large-scale Strategic Site Development
-
- ‘16.8.
- Completed Traffic Impact Assessment Review and Strategic Environmental Impact Assessment