Project Progress

Magok Urban Development Project Overview

마곡도시개발사업 개요 정보
Location Magok-dong area, Gangseo-gu
Areas 3,669,000㎡ (District 1: 1,104,000㎡, District 2: 1,866,000㎡, District 3: 699,000㎡)
Total Project Cost KRW 7.2496 trillion
Project Period ’07.12.~ ’24.12.(As of September 2024, Districts 1,2 complex development progress rate 99.9%)
1지구, 2지구, 3지구

District 1 (Residential):12,429 households (6,214 for sale, 6,215 for rent)

  • Phase 1 (’11.9. ~ ’14.6.) : 9 complexes, 6,730 households completed

  • Phase 2-1 (’13.12. ~ ’17.4.) : 5 complexes, 2,985 households completed

  • Phase 2-2 (’17.1. ~ ’after 20) : 1 complex, 1,529 households completed / 2 complexes, 1,185 households in progress

District 2 (Industrial Site Land Sales and Construction)

Land sales : 603,000㎡ occupancy contracts with 208 companies (82.7% of total 729,000㎡)

Industrial Complex Land Supply Status (Unit: ㎡)

산업단지 토지공급 현황 정보
Category Total Site Area 2024 performance (cumulative)
Total 811,498 670,332(82.6%)
Industrial Facility Sites 729,006 603,233(82.7%)
Support Facility Sites 82,492 67,099(81.3%)

Status of Tenant Companies

  • Before 2017 (74 companies): LG, Lotte, Kolon, E-Land, etc.

  • 2018 (27 companies): Lotte Shopping, Osstem Implant, etc.

  • After 2019 (107 companies): Handok, OURHOME, Daewoong Pharmaceutical, etc.

  • Magok Industrial Complex Information System: http://magoksandan.kr/

District 3 (Seoul Botanic Park): Business transferred to Garden City Bureau (Grand opening May 2019)

  • Development Area: 503,000㎡, urban botanical garden + lake park

  • Space Composition: botanical garden, lake park, open forest park, wetland ecological park

  • Main facilities: Plant Culture Center with greenhouse, Han River pedestrian bridge, interchanges, LG Art Center, etc.